Four regulatory frameworks drive most asbestos testing. Each has its own trigger, method and enforcing authority.
AHERA: schools
- All K-12 schools must be inspected for ACM, and re-inspected every 3 years, under 40 CFR Part 763.
- After abatement, air clearance by TEM (40 CFR 763 App. A) is required before reoccupancy. The clearance criterion is 70 s/mm².
OSHA: workers
- 29 CFR 1926.1101 (construction) and 1910.1001 (general industry): PEL 0.1 f/cc TWA, AL 0.1 f/cc.
- An initial exposure assessment is required when workers may disturb ACM or PACM.
- PCM by NIOSH 7400 is the OSHA-accepted method. Results must be available within 5 working days.
NESHAP: demolition and renovation
- EPA 40 CFR Part 61 Subpart M applies to all demolition and significant renovations.
- The owner or operator must survey for RACM before demolition. Bulk PLM results drive the notification requirement.
- RACM threshold: ≥160 sq ft friable, ≥260 linear ft, or ≥35 cubic ft.
Waste disposal: NJ and NY
- Demolition waste containing ACM must be classified as hazardous or non-hazardous before disposal.
- Waste classification submitted to NY DEC or NJ DEP needs NY ELAP accredited methods.
- For non-friable material, NOB by PLM (Item 198.6) determines whether the friability threshold is exceeded.
Other common triggers
- Renovating a pre-1980 building: identify ACM before work begins.
- A litigation or insurance dispute: you need a defensible chain of custody and a PLM and TEM report.
Which test answers which rule
| Framework | Test | IRIS accreditation |
|---|---|---|
| AHERA | TEM air clearance, bulk PLM surveys | NVLAP 600211-0 and NY ELAP #12738 |
| OSHA | PCM air, NIOSH 7400 | NJ NELAP and NY ELAP |
| NESHAP | Bulk PLM | NVLAP 600211-0 |
| Waste disposal | Waste solids by PLM or TEM, NOB | NY ELAP #12738 and NJ NELAP |
One lab, one chain of custody and one report can cover all four frameworks.
Next step
- Air samples: Start the asbestos air COC
- Bulk and waste samples: Start the asbestos bulk COC
For help matching your project to a method, contact the lab or email support@irislaboratories.com.
Chain of custody
Pick the form that matches your test.
Start this COCDownloads
Downloads are behind sign-in.
Sign in to downloadRelated topics
Collecting an asbestos bulk sample, step by step
How to prepare the area, take a representative piece, double-bag and seal it, and label each bag so the lab can match it. Covers the mistakes that cause a resample.
Asbestos air clearance sampling after an abatementSoon
Setting up pumps for final clearance, calculating volume from flow rate and run time, and what AHERA requires before you can release the space.
Asbestos in soil: sampling a site properlySoon
Grid sampling, depth, compositing rules and how much material the lab needs. Why soil is not the same as a bulk building material.
Asbestos in vermiculite insulationSoon
Why vermiculite needs its own approach, how much to collect from an attic, and what a negative PLM result does and does not tell you.